Thursday 20 March 2014

Stage one activities


We went on a weekend around mid February and noticed the water tap is already installed. Few days later we also received the bill with connectivity charges. PD managed the time quite well and they have been working in the background in connecting the utilities while waiting for the building approval. BC gave us a call and informed they are planning to start the construction work by end of Feb. However the dates got postponed due to an approval that has to be taken from the owners of the neighbouring house.

Soon after signing the contract in the second week of January, we informed PD to provide the building approval since that needed to be submitted to the bank. This was a prerequisite from the bank in order to fund the loan.


PD also made arrangements immediately to update the engineering plans to include the partially constructed neighboring house. Here is a list of activities expected to take place during first stage of the construction.